The Transmission Company of Nigeria (TCN) has announced a planned outage on the 132kV Katsina-Daura Double Circuit Transmission Line to enable the relocation and reconstruction of two transmission towers along the railway corridor.
The announcement was contained in a statement signed by TCN Management and dated November 28, 2026.
The outage, which commenced on Saturday, November 28, will run through Sunday, November 29, from 9:00am to 5:00pm daily.
TCN’s Katsina Sub-Region said the planned outage was necessary to facilitate railway crossing reconstruction works being undertaken by Energo Engineering.
The works involve the relocation of transmission towers T225 and T226, as well as the extension of their heights to provide adequate clearance for the new Kano-Maradi Railway Line.
The company said the adjustment of the affected transmission infrastructure was required by the ongoing construction of the railway project.
According to TCN, the outage will enable the reconstruction works to be carried out safely and efficiently, while ensuring the protection of personnel and transmission infrastructure throughout the exercise.
The transmission company apologised to electricity customers in the affected areas for any inconvenience the planned outage might cause.