* Reiterates need for host communities to protect power assets
Several electricity consumers and community leaders in Bauchi metropolis gathered in the Bauchi Transmission Substation, Bauchi to witness the official inauguration of a new substation and four newly installed power transformers to boost stability and flexibility of bulk supply in the Bauchi subregion.
The Honorable Minister of Power, Joseph Tegbe, was on ground to perform the inauguration. According to the Minister, “The history of this project illustrates the challenge we are determined to overcome.
“The New Bauchi Transmission Substation was originally a 132/33K facility with an installed capacity of 112.5MVA, comprising 22.5MVA, 30MVA and 60MVA transformers. As electricity demand increased, this capacity became inadequate, resulting in significant suppressed load.
“Through this intervention, the facility has been upgraded to a 330/132/33kV Transmission Substation, with the installation of two 150MVA, 330/132kV transformers, providing an upstream transformation capacity of 300MVA.
“At the downstream level, the existing 22.5MVA and 30MVA transformers have been replaced with two 60MVA units, while the existing 60MVA transformer has been retained. Consequently, downstream transformation capacity has increased to 180MVA. This represents a substantial improvement in the station’s ability to serve growing electricity demand.
He stated that these investments would improve operational flexibility and provide a stronger platform for reliable electricity delivery to the communities. It is estimated that additional 75,600 households will benefit from this intervention.
The Minister assured that “across the country, the Federal Government is strengthening transmission infrastructure with a clear economic purpose, especially the corridors where economic activity depends upon reliable power.
“We are also working to align investments across generation, transmission and distribution. Our approach is increasingly anchored on the simple proposition that every investment in electricity infrastructure must ultimately translate into measurable economic and social value. “
Before concluding his address, the minister made a strong appeal to the community members and leaders on the need to protect all power assets. He said, “I make a direct appeal: help us keep this facility safe. The cost of vandalism is felt in interrupted trade, lost working hours and disrupted family life.
Public infrastructure serves all of us, and its protection requires the vigilance of all of us.”
The Managing Director/CEO, TCN, Engr Sule Abdulaziz had earlier stated that the “project
intervention has strengthened bulk power supply delivery to Jos Electricity Distribution Company (JEDC), providing greater capacity at the transmission-distribution interface that supports electricity distribution to customers across the befitting communities, subject to available generation and downstream network capacity.
“The benefitting areas under JEDC include Ningi, Dass, Bauchi GRA, Yankari, Nabordo, Dabo Farm and Gubi.
“The project, awarded in January 2021 and completed in June 2026, was executed by a joint venture of MBH Power Limited and Shreem Electric Limited, with funding from the World Bank. Its successful delivery involved extensive engineering, equipment installation, testing and commissioning works.
“We appreciate the World Bank’s support and acknowledge the contributions of the project contractors, consultants and all TCN engineers who participated in bringing the project to completion.
“While the completion of this project is a significant milestone, our responsibility at TCN extends beyond the delivery of new infrastructure. We must continue to ensure that these assets are properly operated, maintained and managed to deliver sustained value to the transmission network.
“Our focus remains on strengthening of network capacity, improving transmission infrastructure,reducing operational constraints and ensuring that available electricity can be transmitted efficiently and reliably.
“At TCN, we remain committed to the systematic expansion and reinforcement of the national transmission network through strategic infrastructure investments and improved operational practices. The Bauchi upgrade is another addition to this ongoing effort.”